The most easy pit to step on is the first WiFi certification in the new park: equipment has been bought, AP is loaded, AC is configured and the top-up user cannot connect, page can't play, authentication is successful but not online. The problem is not that it comes out of a device, but that the need for prior needs is not cleared and implementation steps are not followed in order. From the recognition of needs, there is at least seven phases of demand collection, site surveying, programme selection, equipment deployment, configuring, commissioning, and back-to-back.
Step 1: Collect needs first to find out who wants to be online
A lot of projects come up and ask."What equipment?"I should have answered first."Who wants to get online, how long, what you want to see?"The number of users in the campus is clearly distinguished: number of regular staff, number of visitors per day, number of fixed equipment in the production workshop, number of rooms used several times a day and number of households in the accommodation area. These figures directly determine the number of APs that follow, the number of certificates issued, the size of the address pool and bandwidth planning.
Step 2: Field survey, not measuring the signal, or ping-poo.
The site survey is based on three main things: building structures, existing networks, electricity and cabling. The structure determines the AP location: whether the office building is open or a small room with many partitions, how many rooms per floor are in the accommodation building, and whether there are metal devices to cover the production workshop. The network decides where to authenticate the equipment: where to put the core switch, what brand of export firewalls, how to split VLAN from the inner net, and whether it is already used AC. Power and cabling determines whether AP can use POPE: if there are any weak electrical booths on each level, if there are six types of wire that can be pulled to the AP position, and POE exchange power is not enough. A map of the tops and AP points was surveyed, from which the list of equipment followed.
Step 3: Options, structure first and brand first
The first decision-making option is a certification approach: whether staff use Portal or 802.1X, visitors use text messages or code-scanting, and the MAC white list for fixed equipment. The second decision is to deploy architecture: NATSHEL_AUTH_GATEWAY collage or sidewalking. The side deployment is small and suitable for an already functioning park; the serial deployment controls are more thorough and suitable for new campuses. The third decision is to match AC and AP: AC supports Express Portal, RADIUS docking, VLAN underpass, AP covers office buildings, dormitories, and outdoors. The fourth decision is to certify the server: whether a single or a double-bed machine is deployed, and more than 500 users are expected to consider dual-lined.
Step 4: Equipment deployment, bottom-up by network level
The deployment order is not disrupted: the wiring of APs, then POPE switches and assembly exchanges, and then the loading of ACs and authentication servers and final exits. The APs are well-established: the office buildings have a vacuum cap in the middle of the corridor or ceiling, the accommodation buildings have a panel AP to replace 86 boxes in the room with a waterproofing AP in the outdoor area on either street lights or utility poles. Each AP has an SSID: staff SSID, visitors SSID, production SSID separate from VLAN. After the configuration of the ACs, all APs register to ACs and send SSIDs, their channel, power and strength together. This stage should not be rushed to start authentication, first of all, by wiring and browsing, ensuring that any location signal strength is above -65dBm.
Step 5: Test the set.
The combination tests are the most easy to skip, but least time-consuming. Simulate the real user use: staff members on their mobile phones have SSIDs, enter a password for the account, see whether Portal pages pop up normally, if they can be used online after authentication and if they can access OAs. Visitors on visitors to visitor SSIDs, when they turn over cell phone numbers, see if they receive them, if they can get Internet access, but not if they can access it. Use the MAC white list for fixed devices, see if they can automatically release them. Final altimeter co-match: Simulate dozens of devices and authenticate them at the same time, see if the authentication server is able to be carded. Each scene test records the results, finds the problem on the spot and does not leave it behind.
Step 6: Run on a trial run, two weeks to find a real user.
The risk of one-time access is too high for the entire campus. The right approach is to select a building for a trial run, which will allow 50 to 100 real employees to run for two weeks. These two weeks focus on three types of problems: problems that do not connect users (cell compatibility, weak signal, password error), problems that do not pop up (HTTPS redirection, browser intercepting) and problems that are successful but not online (VLAN configuration error, ACL rule error, DNS failure). During the test operation, IT has to look daily at the certification logs, account for failures and centralize high frequency issues. A list of issues was drawn up after the trial operation and the entire campus was repaired.
Step 7: official online, batched
The first day of the visit is open, the next day is added to the cafeteria, the third day to the dormitory and the last day outside. A half-day observation after each batch is made to see whether there are any irregularities in certification success rates, online users, bandwidth occupancy. On the same day, IT is on duty, preparing for a self-help guide (printing small cards on walls) to address common problems, and users can't find IT until they have a card.
The three most easy pits to step on from zero to one.
The first pit is a simple purchase of equipment without planning. The AP number takes the head on floor, resulting in high-secret scene signal congestion; the address pool matches C mask code, and more than 254 online users do not get IPs. The second pit is designed only for machine rooms. All functions are full, so when the metal equipment is covered up in the workshop and the real environment falls down on the walls of the dormitory, it's another thing. The third hole is a non-user notification. The correct approach was to send a notice three days before the visit, telling you how WiFi is connected, what account number, how many initial passwords are and where the access code has been changed.
The WiFi certification for the new campus is essentially a project management issue, not a technical one. It is based on needs, surveying, selection, deployment, alignment, commissioning, and seven steps up-line, each step to confirm the confirmation will not be used to save fires.